Fort Bragg Municipal Broadband Utility Project

Last Updated: February 6, 2026

Schedule subject to change due to weather or unforeseen conditions.

Questions? Contact Carlos Hernandez, Engineering Technician, by phone at 707-961-2823 ext.130 or by email at chernandez@fortbragg.com.

Daytime Work (8am – 4:30pm)
Night Work (7pm – 5am)

Week of February 2, 2026

Friday, February 6
8:00am – 4:30pm
Alley West of Stewart St
Directional boring and utility box installation
N Main St (North of Airport Rd) Night
Directional boring and utility box installation

Week of February 9, 2026

Monday, February 9
8:00am – 4:30pm 7:00pm – 5:00am
Alley West of West St
Directional boring and utility box installation
Alley between S Harrison & S Whipple St
Handhole and fiber pedestal installation
Cypress Street
Utility box installation
N Main St & Bush St Night
Directional boring and utility box installation
Tuesday, February 10
8:00am – 4:30pm 7:00pm – 5:00am
Alley West of West St
Directional boring and utility box installation
Alley West of Stewart St
Directional boring and utility box installation
Alley between S Harrison & S Whipple St
Handhole and fiber pedestal installation
N Main St & Spruce St Night
Directional boring and utility box installation
Wednesday, February 11
8:00am – 4:30pm 7:00pm – 5:00am
Alley West of West St
Directional boring and utility box installation
Alley West of Stewart St
Directional boring and utility box installation
Alley between N Harrison & N Whipple St
Handhole and fiber pedestal installation
N Main St & Elm St Night
Directional boring and utility box installation
Thursday, February 12
8:00am – 4:30pm 7:00pm – 5:00am
Alley West of West St
Directional boring and utility box installation
Alley West of Stewart St
Directional boring and utility box installation
Alley between N Harrison & N Whipple St
Handhole and fiber pedestal installation
N Main St (North of Airport Rd) Night
Utility box installation
Friday, February 13
8:00am – 4:30pm 7:00pm – 5:00am
Alley West of West St
Directional boring and utility box installation
Alley West of Stewart St
Directional boring and utility box installation
Alley between N Harrison & N Whipple St
Handhole and fiber pedestal installation
N Main St (North of Airport Rd) Night
Utility box installation

Week of February 16, 2026

Monday, February 16
8:00am – 4:30pm
Alley between S Harrison & S McPherson St
Handhole and fiber pedestal installation
Tuesday, February 17
8:00am – 4:30pm
Alley between S Harrison & S McPherson St
Handhole and fiber pedestal installation
Wednesday, February 18
8:00am – 4:30pm
Alley between N Harrison & N McPherson St
Handhole and fiber pedestal installation
Thursday, February 19
8:00am – 4:30pm
Alley between N Harrison & N McPherson St
Handhole and fiber pedestal installation
Friday, February 20
8:00am – 4:30pm
Alley between N Harrison & N McPherson St
Handhole and fiber pedestal installation

Schedule subject to change due to weather or unforeseen conditions.

Questions? Contact Carlos Hernandez, Engineering Technician, by phone at 707-961-2823 ext.130 or by email at chernandez@fortbragg.com.