Fort Bragg Municipal Broadband Utility Project

Last Updated: May 11, 2026

Schedule subject to change due to weather or unforeseen conditions.

Questions? Contact Carlos Hernandez, Engineering Technician, by phone at 707-961-2823 ext.130
or by email at chernandez@fortbragg.com.

Daytime Work (8am – 4:30pm)
Night Work (7pm – 5am)

Week of May 18, 2026

Tuesday, May 19
8:00am – 4:30pm
Eastside Alleyway (E Bush St to E Fir St)
Directional boring
DA008 Service Area
Terminal cable placement, mounting, and labeling
Handhole crew off
Wednesday, May 20
8:00am – 4:30pm
Eastside Alleyway to N McPherson St
Directional boring
DA008 Service Area
Terminal cable placement, mounting, and labeling
Handhole crew off
Thursday, May 21
8:00am – 4:30pm
Eastside Alleyway (E Bush St to E Fir St)
Directional boring
DA008 Service Area
Terminal cable placement, mounting, and labeling
Handhole crew off
Friday, May 22
8:00am – 4:30pm
Eastside Alleyway (E Bush St to E Fir St)
Directional boring
DA008 Service Area
Terminal cable placement, mounting, and labeling
Handhole crew off

Week of May 25, 2026

Tuesday, May 26
8:00am – 4:30pm
Eastside Alleyway (E Bush St to E Fir St)
Directional boring
Alley between N Main St & N Franklin St
Drilling, trenching, and handhole installation
Wednesday, May 27
8:00am – 4:30pm
Eastside Alleyway (E Bush St to E Fir St)
Directional boring
Alley between N Main St & N Franklin St
Drilling, trenching, and handhole installation
Thursday, May 28
8:00am – 4:30pm
Eastside Alleyway (E Fir St to N McPherson St)
Directional boring
Alley between N Main St & N Franklin St
Drilling, trenching, and handhole installation
Friday, May 29
8:00am – 4:30pm
Eastside Alleyway (E Fir St to E Pine St)
Directional boring
Alley between N Main St & N Franklin St
Drilling, trenching, and handhole installation

Week of June 1, 2026

Monday, June 1
8:00am – 4:30pm
Alley between N Main St & N Franklin St
Drilling, trenching, and handhole installation
Tuesday, June 2
8:00am – 4:30pm
Alley between N Main St & N Franklin St
Drilling, trenching, and handhole installation
Wednesday, June 3
8:00am – 4:30pm
Alley between N Main St & N Franklin St
Drilling, trenching, and handhole installation
Thursday, June 4
8:00am – 4:30pm
Alley between N Main St & N Franklin St
Drilling, trenching, and handhole installation
Friday, June 5
8:00am – 4:30pm
Alley between N Main St & N Franklin St
Drilling, trenching, and handhole installation

Schedule subject to change due to weather or unforeseen conditions.